ISQI CTAL-TM_Syll2012 certification exam is an important certification for software testing professionals who want to advance their careers in test management. By passing this certification exam, candidates can demonstrate their knowledge and skills in managing and leading testing teams, developing test strategies, and ensuring the quality of the testing process. With thorough preparation and dedication, candidates can increase their chances of passing the certification exam and achieving this valuable certification.
NEW QUESTION # 62
Assume that you are the Test Manager for a small insurance application development project.
You have decided to adopt a risk-based testing strategy: 5 product risks (R1, R2, R3, R4, R5) have been identified and their levels of risk have been assessed. 10 test cases (T1, ..., T10) have been designed to cover all the product risks.
The following table shows the risk level and the test cases associated to the identified product risks (higher risk level means higher risk):
You are not confident with the assessment of the risk level and you suspect that it will be possible to find high-priority bugs in low-risk areas.
Furthermore the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing.
Which of the following answers describes the best test execution schedule in this scenario?
K3 2 credits
- A. T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
- B. T10, T8, T6, T4, T2, T9, T7, T5, T3, T1
- C. T1, T3, T5, T7, T9, T2, T4, T6, T8, T10
- D. T10, T9, T8, T7, T6, T5, T4, T3, T2, T1
Answer: C
NEW QUESTION # 63
After the presentation, you are asked to explain the chart.
Assume you have applied a full risk-based testing strategy.
Which of the following answers would you expect to best describe the pie chart?
K4 3 credits
- A. All the risk items have been covered with tests. No more risk items remain to test
- B. Only the lowest-risk items, tests and bugs should remain in the blue and red areas. Therefore the application can be released at any time subject to management of the items identified in those areas
- C. According to the full risk-based testing strategy applied, it is very likely that the highest-risk items, tests and bugs remain in the blue and red areas. Therefore, it is very risky to release the application
- D. 97 percent of the risk items has been tested. No open bugs or test failures remain. Only 3 percent of risk items remains to be covered by the remaining test
Answer: B
NEW QUESTION # 64
Consider the following skills assessment spreadsheet for your test team (consisting of four team members):
This spreadsheet has three sections: technical expertise, testing skills and professionalism.
The skill levels for each skill area for both the "technical expertise" and "testing skills" sections have been rated on a four-point scale:
-E (Expert): indicates that a person has expert knowledge and experience in the skill area
-B (Beginner): indicates that a person has some knowledge and experience in the skill area but he/she is not autonomous
-W (Wants to learn): indicates that a person has no knowledge or experience in the skill area but he/she wants to learn that skill
-NI (Not Interested): indicates that a person has no knowledge or experience in the skill area and he/she is not interested to learn that skill
The skill levels for each skill area of the "professionalism" section have been rated on a three point scale (H=High, M=Medium, L=Low).
Consider the following analysis of testing skills performed on four peoplE. Alex, Robert, John and Mark (all the skills have been rated on an ascending scalE. The higher the score, the better the skill): Which of these people, based on this analysis, would you expect to be most suitable to work specifically as test designer?
K4 3 credits
- A. Alex
- B. John
- C. Mark
- D. Roberta
Answer: D
NEW QUESTION # 65
Test Management
Assume you are managing the system testing phase of a project.
The system test execution period is scheduled to twenty weeks.
All tests are manual tests. You are following a risk-driven test approach.
During the last staff meeting the project manager tells you new deadlines that will not allow completion of all the system tests.
Which of the following would you expect to be the best way to respond to this situation?
- A. Remove testers from your test team, so that they can be assigned to other projects
- B. No action is needed, test as much as possible in the remaining time period
- C. Prioritize executing the tests for the highest product risks and track these risks
- D. Automate all remaining tests
Answer: C
Explanation:
Section: Test Management
NEW QUESTION # 66
Defect Management
Consider a defect report and assume that a part of its lifecycle includes the following states:
New: Is the initial state
Working: Means that the developers are addressing the defect in order to produce a fix for the defect Clarification: Means that the developers need more information from the tester to address the defect and produce a fix for the defect and the tester is working to provide this information to the developers Verification: Means that a fix for the defect has been produced and the tester is running the adequate tests to verify whether the fix solves the defect Closed: is the final state Which of the following answers represents an invalid sequence of states that can't lead the bug report to the
"Closed" state?
Number of correct responses: 1
K2 1 credit
- A. New, Working, Verification, Working, Clarification, Working, Verification, Closed
- B. New, Working, Verification, Closed
- C. New, Working, Verification, Working, Clarification, Working, Closed
- D. New, Working, Clarification, Working, Verification, Closed
Answer: C
NEW QUESTION # 67
Consider the following statements describing the importance of improving the test process:
I. Test process improvement is important because being focused only on the test process it can provide recommendations to improve the test process itself, but it can't indicate or suggest improvement to areas of the development process
II. Test process improvement is important because it is much more effective than software process improvement to improve the quality of a software system
III. Test process improvement is important because several process improvement models (STEP, TPI Next, TMMi) have been developed over the years
IV. Test process improvement is important because every organization, regardless of the context, should always achieve the maximum level of maturity of testing described in the test improvement models such as TMMi
Which of the following answers is correct?
K2 1 credit
- A. I., II., III. and IV are false
- B. I., II. and III are true; IV. is false
- C. I., II. and III. are false; IV. is true
- D. I. and IV. are true; II. and III. are false
Answer: A
NEW QUESTION # 68
Improving the Testing Process
Which of the following statements about the TMMi test process improvement model is true?
Number of correct responses: 1
K2 1 credit
- A. TMMi has a staged architecture for process improvement with seven maturity levels
- B. At TMMi level 1 testing is chaotic without a defined process, and it is often seen as the same as debugging
- C. In TMMi all the process areas at lower levels must be 75% complete by achieving specific and generic goals in order to claim the higher level
- D. TMMi provides an approach for test process improvement such as the IDEAL (Initiating, Diagnosing, Establishing, Acting and Learning) model
Answer: B
NEW QUESTION # 69
During the follow-up phase the following conditions are checked:
X1. The code has been completely reviewed
X2. All the identified defects have been correctly fixed and the modified code has been compiled successfully and run through all the static analyzers used by the project without warnings and errors
X3. The modified code is available under the configuration management system with a new version number for the specified CI
If these conditions are fulfilled then the review process terminates.
Which of the following characteristics of a formal review is missing in this description?
K2 1 credit
- A. Deliverables such as reports, evaluation sheets or other review summary sheets
- B. Defined entry and exit criteria
- C. Metrics for reporting on the review effectiveness, efficiency, and progress
- D. Checklists to be used by the reviewers
Answer: C
Explanation:
Topic 2, Test Management
NEW QUESTION # 70
You are performing a quality risk analysis for a CSCI (Computer Software Configuration Item) used to implement a CBIT (Continuous Built-In Test) module of a safety-critical system.
During the quality risk analysis you are trying to identify the ways in which failures of the CBIT module can occur, for each of them trying to determine the potential causes and likely effects, and the risk level (calculated as the product of three factors: severity, occurrence and detection).
Which of the following risk analysis techniques are you working with?
K2 1 credit
- A. Failure Mode and Effect Analysis
- B. A lightweight product risk analysis technique
- C. Cost of Exposure
- D. Wide Band Delphi
Answer: A
NEW QUESTION # 71
Test Management
Assume you are currently working on a project developing a system where functional requirements are very well specified. Unfortunately non-functional requirements do almost not exist.
You are the Test Manager. You have to choose a technique for test selection that allows testing of non-functional characteristics, especially reliability.
Which of the following techniques for test selection do you expect being most useful in this scenario?
Number of correct responses: 1
K2 1 credit
- A. Cause-effect graphing
- B. Ambiguity reviews
- C. A model-based technique based on the creation of operational profiles
- D. Test condition analysis
Answer: C
NEW QUESTION # 72
You are not confident with the assessment of the risk level and you suspect that it will be possible to find high-priority bugs in low-risk areas.
Furthermore the period for test execution is very short. Your goal is to test all the product risks in a risk-based way, while assuring that each product risk gets at least some amount of testing.
Which of the following answers describes the best test execution schedule in this scenario?
Number of correct responses: 1
K32 credits
- A. T1, T2, T3, T4, T5, T6, T7, T8, T9, T10
- B. T10, T8, T6, T4, T2, T9, T7, T5, T3, T1
- C. T1, T3, T5, T7, T9, T2, T4, T6, T8, T10
- D. T10, T9, T8, T7, T6, T5, T4, T3, T2, T1
Answer: C
NEW QUESTION # 73
During the follow-up phase the following conditions are checked:
X1. The code has been completely reviewed
X2. All the identified defects have been correctly fixed and the modified code has been compiled successfully and run through all the static analyzers used by the project without warnings and errors X3. The modified code is available under the configuration management system with a new version number for the specified CI If these conditions are fulfilled then the review process terminates.
Which of the following characteristics of a formal review is missing in this description?
Number of correct responses: 1
K2 1 credit
- A. Deliverables such as reports, evaluation sheets or other review summary sheets
- B. Defined entry and exit criteria
- C. Metrics for reporting on the review effectiveness, efficiency, and progress
- D. Checklists to be used by the reviewers
Answer: C
NEW QUESTION # 74
Your application development team is performing "test-driven" development. This is a core principal of which software development model?[1]
- A. Spiral
- B. Iterative
- C. Agile
- D. Sequential
Answer: C
Explanation:
Test-driven development (TDD) is a core principle of Agile software development. In TDD, test cases are created before the code is written, and the code is developed to pass these tests. This approach emphasizes requirements and solutions evolving through collaborative effort and is a key practice in Agile methodologies12.
References:The Agile Alliance describes TDD as a style of programming tightly interwoven with coding, testing, and design, which is a fundamental aspect of Agile development3. Wikipedia also notes that TDD is related to the test-first programming concepts of extreme programming, an Agile methodology This is because test-driven development (TDD) is a style of programming in which coding, testing, and design are tightly interwoven. TDD is a core principle of agile software development, which is an iterative and adaptive approach that values customer collaboration, working software, and responding to change. Agile Alliance References: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, What is Test Driven Development (TDD)? | Agile Alliance
NEW QUESTION # 75
Test Management
You are working on a project to develop an authentication system for an e-commerce website. This system provides two features: Registration and authentication. Two different development teams develop these two features.
There is a high likelihood that the delivery of the authentication feature to the test team will be three weeks later. To complete the registration the user must provide the following registration inputs: Name, surname, birthdate, fiscal code and he/she can select a username and a password.
A registered user can be a special user or a normal user. To be identified as a special user, he/she must also provide, during the registration process, a voucher possibly received from the IT department.
Access is granted only if a user is registered and the password is correct: In all other cases access is denied. If the registered user is a special user and the password is wrong, a special warning is shown on the system console.
You are currently performing a quality risk analysis using FMEA.
Based only on the given information, which of the following is NOT a product risk that could be identified during the quality risk analysis?
- A. The late delivery of the authentication feature to the test team causes delays in the start of test execution and this could result in a shorter test period
- B. The authentication system denies access for a special user with a wrong password, but doesn't display a special warning on the system console
- C. The authentication system grants access to a special user with a wrong password
- D. The authentication system grants access to a normal user with a wrong password
Answer: A
Explanation:
Section: Test Management
NEW QUESTION # 76
Test Management
Which of the following statements describing how identified product quality risks should be mitigated and managed, is true?
Number of correct responses: 1
K2 1 credit
- A. The extent of re-testing and regression testing activities should be based on the risk level
- B. Risk mitigation of product quality risks can be effective only after starting test execution
- C. The identification of new risks, the re-assessment of the level of existing risks and the evaluation of the effectiveness of risk mitigation activities should only occur at the very beginning of a project
- D. The priority of the development and execution of tests should not be based on the risk level but only on the likelihood
Answer: A
NEW QUESTION # 77
Which of the following is a key characteristic of a management review? [1]
- A. Used to check consistency of and deviation from the system requirements
- B. Conducted by an external group to assess process compliance
- C. Used to assess project risks
- D. Run by a moderator
Answer: B
Explanation:
A management review, particularly in the context of software testing and quality assurance, often involves an external group or higher-level management team that reviews the processes and procedures to ensure compliance with specified standards or objectives. This can include assessing the effectiveness of current practices, identifying areas for improvement, and ensuring that the project aligns with organizational or industry standards. This type of review is distinct from other forms of reviews like technical reviews or walkthroughs, which might focus more on the technical aspects or consistency of system requirements.
NEW QUESTION # 78
Test Tools and Automation
Assume you are a Test Manager involved in system testing of a CRM application for a Pay-TV company.
Currently the application is able to support a proper number of users assuring the required responsiveness. Since the business is expected to grow, you have been asked to evaluate the ability of the application to grow to support more users while maintaining the same responsiveness.
Which of the following tools would you expect to be the most useful at performing this evaluation?
- A. Performance tools
- B. Static analysis tools
- C. Test management tools
- D. Coverage tools
Answer: A
NEW QUESTION # 79
Which of the following is likely to occur if reviewers do not have an adequate level of technical knowledge?
[1]
- A. The review will be shorter because any technical aspect can be skipped.
- B. There will be no impact as long as they have sufficient business knowledge.
- C. The review is likely to be less efficient.
- D. There will be no impact as long as they have sufficient process knowledge.
Answer: C
Explanation:
If reviewers do not have an adequate level of technical knowledge, they may not be able to identify and describe anomalies in the product or project under review1. They may also not be able to provide constructive feedback or suggestions for improvement2. This can result in a less efficient review, as the review objectives may not be met, the review process may take longer, or the review outcome may be of lower quality3.
Therefore, option C is the correct answer. Option A is incorrect because having sufficient business knowledge is not enough to perform a technical review, as business knowledge does not cover the technical aspects of the product or project4. Option B is incorrect because having sufficient process knowledge is not enough to perform a technical review, as process knowledge does not cover the technical aspects of the product or project4. Option D is incorrect because skipping any technical aspect can compromise the quality and completeness of the review, and may lead to defects or risks in the product or project5. References: 1: ISTQB Glossary, Reviewer 2: ISTQB Advanced Level Test Manager Syllabus, Section 2.2.2 3: ISTQB Advanced Level Test Manager Syllabus, Section 2.2.3 4: ISTQB Advanced Level Test Manager Syllabus, Section
2.3.1 5: ISTQB Advanced Level Test Manager Syllabus, Section 2.3.2
NEW QUESTION # 80
Which of the following would you expect to be most likely an example of a motivating factor for testers?
K2 1 credit
- A. The testers contribution to the quality of the software products developed from an organization is recognized with increased responsibilities
- B. The testers are asked to perform, in parallel with their testing tasks, other tasks unrelated to their testing responsibilities
- C. The same regressions tests are executed manually by the same testers, for every product release, without any progression in content
- D. The resources allocated for the testing activities are not sufficient and don't allow the testers to contribute to the quality of the product
Answer: A
NEW QUESTION # 81
What is a "depth-first" risk-based testing technique? [1]
- A. Highest risk test cases are executed first
- B. Lowest risk test cases are executed first
- C. Non-functional test cases are executed first
- D. All risk items are tested at least once
Answer: A
Explanation:
A depth-first risk-based testing technique is a method of prioritizing and executing test cases based on the risk level of the features or functions to be tested. In this technique, the test cases with the highest risk are executed first, followed by the test cases with lower risks. This ensures that the most critical and likely areas of failure are tested thoroughly and early in the testing process. Risk Based Testing: Approach, Matrix, Process & Examples - Guru99 References: Certified Tester Advanced Level Test Manager (CTAL-TM) - ISTQB not-for-profit association, ISTQB Test Manager Certification - ISTQB Exams Worldwide - ISTQB Official Registration, [Analytical Test Strategy: A Comprehensive Guide - LambdaTest]
NEW QUESTION # 82
Test Management
You are the Test Manager of a new project aimed at developing a software system that must be certified at level B of the DO-178B standard. The project will follow a V-Model software development life cycle and it will have four formal levels of testing: component, integration, system and acceptance testing.
You must produce the test plan documentation for this project by providing an adequate coordination across the four levels of testing in order to assure auditability.
Which of the following answers would you expect to best describe how to organize the test plan?
- A. Produce four separate detailed level test plans, one for each level, without a master test plan
- B. Produce a single master test plan that covers in detail all four levels, describing the particular activities for all test levels
- C. Produce a master test plan describing the relationship between the four levels, and four separate detailed level test plans, one for each level
- D. Produce a master test plan that covers three levels (component, integration, system test) and a separate acceptance test plan
Answer: C