[2021] AACE-PSP Actual Exam Dumps, AACE-PSP Practice Test
DumpsMaterials AACE-PSP dumps & AACE Certification sure practice dumps
How to Prepare For Planning & Scheduling Professional (PSP) Exam
Preparation Guide for Planning & Scheduling Professional (PSP) Exam
Introduction
The Planning & Scheduling Professional PSP exam test is administered by AACE International, the Association for the Advancement of Cost Engineering. In 1956, during the organizational meeting of the American Association of Cost Engineering at the University of New Hampshire in Durham, New Hampshire, 59 cost estimators, and cost engineers founded AACE International (Association for the Advancement of Cost Engineering). The International Headquarters of AACE is based in Morgantown, West Virginia, USA. AACE is a specialized non-profit organization. The Board of the Council of Engineering and Technical Specialty Boards (CESB) is a member of AACE International.
AACE operates eight qualification programs at present. Both include the agreement and passing of an evaluation to adhere to a canon of ethics. Most require previous experience in the industry and may provide recertification through continuing education or reexamination. Six of these certifications are accredited by the Council of Engineering and Scientific Specialty Boards (CESB).
This exam guide is intended to aid in achieving AACE’s specialty certification with the best possible grades. It will enable you to understand the scope of the Planning & Scheduling Professional (PSP) Exam and help you to prepare for it successfully by making use of the provided PSP dumps. This guide includes information on the certification test target audience, recommended preparation and documentation, and a full list of exam targets, all to help you obtain a passing grade. To increase your chances of passing the test, AACE strongly recommends a mix of on-the-job experience, course attendance, and self-study, and taking the PSP practice tests. This guide contains useful references for detailed knowledge.
NEW QUESTION 70
Time-scaled logic diagrams are
- A. Logic networks that are drawn to match the calendar.
- B. The same as a pure-logic diagram.
- C. Used to calculate the most probable activity duration.
- D. Only calculated using a computer.
Answer: A
NEW QUESTION 71
Midway through the project you received an executed change order for this project, adding thirty-three days to the contract for weather delays. In its simplest form, how would your next project update display the changed condition?
- A. After Activity 1001, add a new Activity 1011 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
- B. After Activity 1000, add a new Activity 1010 with a finish-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-start relationship to the final activity of the project.
- C. After Activity 1000, add a new Activity 1050 with a start-to-start relationship to Activity 1000, and tie the end of this new activity with a finish-to-finish relationship to the final activity of the project.
Answer: A
NEW QUESTION 72
For which of these delays should an owner grant a time extension?
- A. Shop drawings and centrifuge delay.
- B. Differing site conditions and centrifuge delay.
- C. Differing site conditions at parking structure.
- D. Structural steel shop drawings.
Answer: C
NEW QUESTION 73
Assuming a total of 30 lifts per crane per day, what is the maximum number of lifts that could be accomplished using 3 small tower cranes over a 5-day period?
- A. 450 lifts
- B. 300 lifts
- C. 45 lifts
- D. 150 lifts
Answer: A
NEW QUESTION 74
Which of the following documents is most likely to be of the LEAST value to a planner/scheduler when planning a contractor's baseline critical path schedule for the construction of a large high-clearance bridge located very near an airport? The contractor has been awarded the contract.
- A. The regulations published by the government aviation agency
- B. The project plans and specifications
- C. The project geotechnical report
- D. The government's report on future high-clearance bridge projects
Answer: D
NEW QUESTION 75
How could the structural steel drawing delay have been prevented?
- A. Add a time buffer at the end of structural steel activities.
- B. Switch to post-tensioned concrete construction.
- C. Allow adequate time for review and resubmittal in the baseline schedule.
- D. Release the structural steel for fabrication concurrent with review of structural steel shop drawings.
Answer: A
NEW QUESTION 76
Is activity 7001 pictured correctly in the precedence diagram?
- A. Yes, except the early finish date is not shown.
- B. Yes, the duration is 48 days.
- C. No, the total float is not shown correctly.
- D. No, the start-to-start and finish-to-finish relationships are backwards.
Answer: B
NEW QUESTION 77
If after calculating a schedule an activity exhibits negative total float, which of the following is certain? The activity
- A. Has yet to be completed.
- B. Was completed in the past.
- C. It is on the critical path.
- D. Is a milestone.
Answer: A
NEW QUESTION 78
Which of the following will NOT affect the total float calculation of a non-resource leveled schedule?
- A. Front end loading.
- B. Multiple calendars.
- C. Preferential logic.
- D. Start and finish constraints.
Answer: A
NEW QUESTION 79
Why does activity 1001 have two successor activities?
- A. Because the late finish of 1001 and the late start of 7001 require two successors
- B. Because the problem could not effectively work with only one successor
- C. Because there are two defined logic paths for the work
- D. Because the duration of activities 2001, 2002 and 200.f require two successors
Answer: C
NEW QUESTION 80
At a minimum, periodic reporting must be done at what interval?
- A. As requested by the project manager.
- B. As specified in the contract documents.
- C. Monthly.
- D. As requested by the owner.
Answer: B
NEW QUESTION 81
Which is NOT an industry-recognized methodology for quantifying critical delay?
- A. Gantt Chart.
- B. Periodic Windows.
- C. Collapsed As-Built.
- D. Time Impact.
Answer: A
NEW QUESTION 82
What is the cycle time?
- A. 17 minutes
- B. 14 minutes
- C. 5 minutes
- D. 6 minutes
Answer: A
NEW QUESTION 83
Using the "normal" schedule, if you start Activity 7001 on April 1, 2002, and using a 5-day workweek, what the finish date for Activity 7001?
- A. 06-04-02.
- B. 06-11-02.
- C. 06-05-02.
- D. 06-18-02.
Answer: C
NEW QUESTION 84
An earned value-based project control system can use either of which two budgets as the basis of its calculations?
- A. Direct or indirect cost.
- B. Earned or budgeted cost yearly.
- C. Labor hours or dollars.
- D. Linear feet or dollars.
Answer: B
NEW QUESTION 85
In its simplest form, what is the main drawback of critical path method scheduling?
- A. It allows for Precedence Diagramming Method to be used in place of Arrow Diagramming Method.
- B. It doesn't account for interdependent between activities.
- C. It requires a backward pass to calculate late dates.
- D. It assumes that resources are unlimited.
Answer: D
NEW QUESTION 86
Using the "crashed" schedule, if you start Activity 2002 on August 12, 2001, what is the finish date for Activity 2002?
- A. 09-18-01.
- B. 09-28-01.
- C. 09-15-01.
- D. 09-08-01.
Answer: D
NEW QUESTION 87
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?
- A. The activities occur in series with a 15-day lag.
- B. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
- C. The activities run concurrently.
- D. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.
Answer: A
NEW QUESTION 88
There is only enough room for a maximum of 4 cranes to be placed on-site. Assuming that a single crane can perform 35 lifts per day and that a column pour requires 60 lifts, what is the minimum number of tower cranes that should be used for the above described column pours?
- A. 3 cranes
- B. 2 cranes
- C. 4 cranes
- D. 1 crane
Answer: B
NEW QUESTION 89
Which of the following is NOT true?
- A. Constraints can interfere with the longest path calculation.
- B. A network must contain only one Critical Path.
- C. Multiple calendars can affect the total float calculation.
- D. Remaining durations can exceed original durations.
Answer: D
NEW QUESTION 90
......
How to book the Planning & Scheduling Professional (PSP) Exam
Follow the steps mentioned below to book the Planning & Scheduling Professional (PSP) Exam:
- Step 1: Visit the AACE’s website by clicking here
- Step 2: Create a new account or log in to an existing account
- Step 3: Select your professional exam
- Step 4: Complete the required course and take PSP practice test
- Step 5: Fill the application and submit all required documents
- Step 6: Schedule your exam by following the instructions on the website